Huish Sixth

All the scaffolding is down and the building name has now been fitted outside the main entrance in stainless steel ‘HUISH SIXTH’. This is an exciting time as it is a reminder that the building work is coming towards the end of the contract. But there is still a lot of work to do and inside the building activity is high.



zoom

All the finishes and fittings are being completed and installed, including carpets, marmoleum, worktops, toilets and disabled toilets. The kitchen fittings have also been delivered and protected on site ready for final fitting. Hoistway are on site installing their platform lifts. There will be one in each block. These lifts, as their name suggests, provide an enclosed platform to assist disabled persons to the first floor. They are not fully enclosed lift cars and are not intended for regular heavy use. They will be available by key control under supervision.

zoom


The science extension is nearing completion and whilst snagging takes place to identify items that require attention, the external works is also being finished. The tarmac play court is being laid and new trees and re-seeding are being established.




zoom

Meanwhile, the dining room extension has its beam and block floor and superstructure brickwork can progress to complete the external walls.

What’s happening next? Over the next few weeks you will see:

• Bridge link works
• Science being handed over to the school
• External works